Projects
Gallego Consulting Services (GCS), Inc. is an approved Caltrans DBE/SMBE firm (#34604) and is providing full-time project support for its client Granite~Myers~Rados, A Joint Venture, on the $400-million Design-Build Garden Grove Freeway (SR-22) Widening Project in Orange County, California.
Project Schedules
GCS was responsible for converting the bid schedule into an approved baseline schedule. In addition, GCS was responsible for resource and cost loading the project schedule. As of 09Nov05, the project schedule shows an on-time finish and contains over 3,700 activities of work.
View Project Web Site www.octa.net/sr22
Photo Documentation
GCS is also providing aerial photo documentation for the Garden Grove Freeway widening project. GCS is charged with aerially photo documenting the SR-22 project site once a month for the duration of the project.
I-5 / SR-22 Interchange, Orange County, California
|